16 May 2014

ParSma e.V. Contribution Report


Aside from the pooled funds of HIP, another group, ParSma e.V. have contributed a total of 1,630.00 Euros (97,871.67 Php) for the repairs of Moamboc Elementary School.

Here is the breakdown on how their contribution was spent:
Total Payments
Date
Items
Php 97,770.00
25-Jan
Iron bars, galvanized iron wires, cement, hollow blocks
      7,875.00
21-Feb
Iron bars, boards, red oxide, nails, marine board
    14,383.00
21-Feb
Jalousies and window frames
      4,333.00
21-Feb
Galvanized iron sheets, red oxide, nails
    10,775.00
21-Feb
Nails, hinges, concrete nails, paint brushes, red oxide, paint thinner
      1,855.00
21-Feb
Red oxide, galvanized iron sheets
      8,258.00
23-Feb
Plywood
      3,080.00
24-Feb
Nails, paints, galvanized irons sheets, sealant, good lumber, sand paper, red oxide, paint thinner, paint brushes, level hose
    15,397.00
24-Feb
Iron bars, cement, umbrella nails
      8,564.00
23-Mar
Galvanized Iron Sheets
    23,250.00












The remaining 101.67Php will be pooled with the common funds of HIP.

Latest photos from the school will be posted next week, once I am back from the islets this weekend.


DAGHANG SALAMAT, ParSma e.V.!